Home > Case Study > PCA Geocell Load Support Solution for Unpaved Road in Oil Field

PCA Geocell Load Support Solution for Unpaved Road in Oil Field

Update time : 2022-02-14

Original Conditions of the Project

The original road was originally a temporary access road in the oil production area. The load capacity was not strong and the road was muddy.

case study4 1(The original condition of the access road)

PCA geocell load support solution

Our PCA geocell are back filled with gravels, as the road is only temporary, so we give an unpaved solution with our high strength PCA geocell. Although it is unpaved, the road can carry 60 tons of large oil tanker to enter the site for operation.

case study4 2(PCA geocell under installation)

case study4 3(Finished project)